Download Product Information2025-12-20T10:49:25-05:00
Conner Product Brochure

What Large Power Transformer Packaging Has to Get Right Before the Bushing Leaves the Dock

Large power transformers ship disassembled, and the bushings, radiators, and conservator tanks that travel separately from the main tank carry more transit risk than most packaging plans account for. With lead times already running 128 to 144 weeks, a shock event on one of those components doesn't end in a freight claim. It ends in a re-test and rebuild cycle stacked onto a queue with no room left to absorb it. Here's what a packaging plan needs to get right before the next unit ships.

Go to Top